Straw Bio Methane Plant at Bhutal Kalan, Punjab |
Supply & Installation of Electrical, Instrumentation & works |
End User:Verbio India Pvt. Ltd, PMC: Neilsoft Engineering Services |
2021 |
75,632 |
EPRO Project, Bayer Vapi Pvt Ltd, Vapi, Gujarat |
Supply & Installation of Electrical & Instrumentation works |
End User: Bayer Vapi Ltd, Consultant : Aker Solutions |
2019 |
241,192 |
Phthalic Anhydride Plant (PA-4) Plant and MA-4 Plant & allied works |
Supply & Installation of Electrical & Instrumentation works |
End User: IG Petrochemicals Ltd, PMC: Aker Solutions |
2018 |
218,579 |
EPCC-05 Revamp Unit at HPCL Visakhapatnam Refinery Modernization Project at Vizag, AP |
Electrical & Instrument Installation |
EPC: Technip FMC, PMC: Engineers India Limited (EIL), End User: HPCL |
2018 |
186,086 |
New Prime G+Unit, New Amine Regeneration Unit (ARU) and offsites & Utilities Area of BS-IV Project at Barauni Refinery, Bihar |
Supply & Installation of Instrumentation works |
Indian Oil Corporation Limited |
2018 |
271,230 |
DEP Project, IG Petrochemicals Limited, Taloja |
Supply & Installation of Electrical & Instrument works |
End User: IG Petrochemicals Ltd, PMC: Neilsoft Engineering Services |
2020 |
119,046 |
ETP Expansion Project, IG Petrochemicals Limited, Taloja |
Supply & Installation of Electrical & Instrument works |
End User: IG Petrochemicals Ltd, PMC: Neilsoft Engineering Services |
2019 |
19,495 |
EFSO Project, Bayer Vapi Pvt Ltd, Vapi |
Instrumentation Erection Job |
Bayer Vapi Private Limited, Vapi |
2018 |
48,350 |
Pilot PIA Project at Patalganga |
Electrical & Instrumentation Job |
Reliance Industries Limited |
2018 |
34,100 |
Ware House Project, Bayer Vapi Pvt Ltd, Vapi, Gujarat |
Supply & Installation of Electrical & Instrumentation works |
End User: Bayer Vapi Ltd, Consultant : Aker Solutions |
2019 |
41,883 |
J3 gasification Jobs – SEZ Gasifier M2, at RIL Jamnagar |
Occasional maintenance of Field Instrumentation Jobs |
Reliance Industries Limited |
2019 |
16,300 |
J3 gasification Jobs –SEZ Sulphur and DTA Sulphur at RIL Jamnagar |
Occasional maintenance of Field Instrumentation Jobs |
Reliance Industries Limited |
2019 |
10,020 |
Hydro-II zinc residue fuming project at HZL, Chanderiya, Rajasthan |
Installation of Electrical, Instrumentation & Telecommunication works |
Hindustan Zinc Limited, EPC: Associated Industrial Furnaces (P) Ltd |
2018 |
310,550 |
LNG Regassification Project at IOLPL, Chennai |
Commissioning Assistance |
Black & Veatch Corporation |
2018 |
57,400 |
CFDV Project, Patalganga, Maharashtra |
Installation of Electrical & Instrumentation works |
Reliance Industries Limited |
2018 |
78,200 |
PREP, DCU, TPS, OMS & SRU Units of IOCL, Panipat Refinery, Haryana |
ARC for Instrumentation Jobs |
Indian Oil Corporation Limited |
2015-18 |
205,050 |
MDF 2 Site at Chittoor, Andhra Pradesh |
Installation of HT/LT Electrical Work |
Green Ply Industries Ltd |
2017 |
101,044 |
BBU, SRU, SWS, ARU, SGU,TGTU & All Utilities / Off sites of Sohar Refinery Improvement Project, Sohar, Oman |
Installation of Electrical, Instrumentation & Telecommunication Works |
ORPIC- Oman Oil Refineries and Petroleum Industries Company, EPC: Daelim - Petrofac JV |
2015 |
1,314,950 |
LCE/Brownfield Expansion Project for CDU/VDU, DCU, Oxygen Unit, BBU, Tank Farm, SRU & VGU Units |
Installation of Electrical Works |
Guru Govind Singh Refinery Bhatinda, EPC: L&T Hydrocarbon |
2016 |
210,745 |
DICO Phase - II Project at Vapi, Gujarat |
Supply & Installation of Electrical & Instrumentation works |
Bayer Vapi Limited |
2017 |
427,666 |
2 x 1000 MTPD, NPK Project, Deepak Fertilizers & Petrochemical Corporation, Taloja |
Supply & Installation of Electrical works |
End User: Deepak Fertilzers & Petrochemical Corporation, PMC: Thyssenkrupp Industrial Solutions |
2016 |
200,697 |
RIL J3 PX4, Reliance Refinery, Jamnagar |
Instrumentation Pre commissioning works |
Reliance Industries Limited |
2016 |
39,500 |
SS Tube Laying for RIL C2 Chemical & Polymer Labs |
Installation of Instrumentation works |
Reliance Industries Limited |
2016 |
45,000 |
CFU, PP, Coker ,Alkylation & PX-4 Units, Reliance Refinery, Jamnagar |
Instrumentation AMC & Field Inst. Modification |
Reliance Industries Limited |
2017-18 |
125,050 |
IDY Project, PMD, Patalganga, Maharashtra |
Installation of Electrical & Instrumentation works |
Reliance Industries Limited |
2015 |
210,298 |
Electrical Works for Construction Power |
Supply & Installation of Electrical Works for Construction Power |
Owens Cornings (India) Pvt. Ltd |
2016 |
49,133 |
Micro Trench Works, Cochin Intracity |
Micro Trenching |
Reliance Corporate IT Park |
2016 |
29,981 |
OFC Laying Works for NLD Route Thiruvalla - Changanacherry |
OFC Laying & Splicing |
Reliance Corporate IT Park |
2016 |
105,000 |
SEZ Steam Super Heater Project at Jamnagar, Gujarat |
Supply & Installation of Electrical & Instrumentation works |
Reliance Industries Limited / Linde Engineering India Ltd |
2016 |
116,775 |
GMP Project at Vapi, Gujarat |
Supply & Installation of Instrumentation works |
Bayer Vapi Limited |
2016 |
26,800 |
Instrumentation Cable Laying Works at Plant 9270,SMPL, Vaadinar, Gujarat |
Supply & Installation of Instrumentation works |
Indian Oil Corporation Limited |
2016 |
21,300 |
DTA Steam Super Heater Project at Jamnagar, Gujarat |
Supply & Installation of Electrical & Instrumentation works |
Reliance Industries Limited / Linde Engineering India Ltd |
2015 |
20,700 |
Electrical works of New Admin Building |
Supply & Installation of Electrical works |
Johnson Matthey chemicals India Pvt Ltd |
2015 |
10,488 |
CFU, PP, Coker ,Alkylation & PX-4 Units, Reliance Refinery, Jamnagar |
Instrumentation AMC & Field Inst. Modification |
Reliance Industries Limited |
2016-17 |
86,800 |
Aerial Cabling Works |
Erection of ADSS Cables |
Reliance corporate IT Park Hyderabad |
2015 |
57,866 |
People Project Active Pharmaceutical Ingredient Facility Ambernath, Maharashtra |
Supply & Installation of Electrical & Instrumentation Works |
Ferring Therapeutics Pvt Ltd, PMC : Bayer Technology, EPC: Mott Mac Donald Pvt Ltd |
2015 |
761,866 |
Integrated Steel Plant, Danapur Village, Hospet, Karnataka |
Installation of Electrical & Instrumentation works |
BMM Ispat Limited |
2015 |
65,666 |
1.89 MTPA Beneficiation Plant, Hospet, Karnataka |
Installation of Electrical Works |
NMDC Ltd, EPC: Hindustan Dorr Oliver Ltd |
2015 |
95,666 |
CFU, PP, Coker & Alkylation, Reliance Refinery, Jamnagar |
Instrumentation AMC & Field Inst. Modification |
Reliance Industries Limited |
2015-16 |
72,400 |
Internal Electrical works, RIL Jamnagar, Gujarat |
Installation of Electrical Works |
Reliance Industries Limited |
2014 |
26,733 |
Ammonia Storage Tank of 10,000 MT Capacity for IFFCO Kalol, Gujarat |
Supply & Installation of Electrical Works |
Uhde India Pvt Ltd |
2013 |
24,666 |
CFU, PP, Coker & Alkylation- Reliance Refinery, Jamnagar |
Instrumentation AMC & Field Inst. Modification |
Reliance Industries Limited |
2013-15 |
207,066 |
PET3 (SSP,AHU & PCY Area) at RIL DMD, Dahej, Gujarat |
Installation of Instrumentation Works |
Reliance Industries Limited |
2013 |
59,500 |
1.8 MTPA Syn Gas based DRI, Angul, Orrissa |
Supply & Installation of Electrical & Instrumentation Works |
Jindal Steel and Power Ltd |
2012 |
383,916 |
1X50 MW Solar Thermal Power Plant, Rajasthan |
Supply & Installation of Electrical & Instrumentation Works |
Lauren Engineers & Constructors (I) Pvt Ltd |
2012 |
52,680 |
2 x 35 MW CPP & Rolling Mill, TUML Plant, Nagpur, Maharashtra |
Installation of Instrumentation Works |
Topworth Urja and Metals Ltd |
2012 |
59,000 |
Ammonia, Urea & OSBL Units of Matix Fertilizer, Durgapur, West-Bengal |
Installation of Electrical and Instrumentation Works |
ESSAR Projects (India) Ltd |
2012 |
383,916 |
Ammonia, Urea & OSBL Units of Matix Fertilizer, Durgapur, West-Bengal |
Installation of Electrical and Instrumentation Works |
Uhde India Pvt Ltd |
2012 |
52,500 |
AVU,STR LPG, SWS 2 units, ARU 2 units for IOCL Refinery, Orissa |
Installation of Instrumentation Works |
ESSAR Projects (India) Ltd, Client – IOCL, Paradeep, PMC – Foster Wheeler |
2012 |
502,000 |
CFU, PP, Coker & Alkylation, Reliance Refinery, Jamnagar, Gujarat |
Instrumentation AMC & Field Inst. Modification |
Reliance Industries Limited |
2012-13 |
80,112 |
Johnson Matthey Chemical-123, Kanpur- Uttar Pradesh |
Supply & Installation of Electrical & Instrumentation Works |
Johnson Matthey Chemical India Pvt Ltd, Consultant: Aker Solutions |
2012 |
79,500 |
PBR Project, Hazira, Gujarat |
Installation of Instrumentation Works |
Reliance Industries Limited |
2012 |
196,750 |
SRU -H2 Plant of Adani Wilmar, Mundra, Kutch, Gujarat |
Supply & Installation of Electrical & Instrumentation Works |
Linde Engineering India Pvt Ltd |
2012 |
22,083 |
SRU Project of HPCL Mumbai Refinery, Maharashtra |
Supply & Installation of Electrical & Instrumentation Works |
EPC: Linde Engineering India Pvt. Ltd, PMC–Jacobs Engineering India Ltd |
2012 |
195,999 |
40 MW Thin Film Solar Power Plant, Kutch, Gujarat |
Supply & Installation of Electrical Works |
ADANI INFRA (India) Limited |
2011 |
300,666 |
CFU, PP, Coker & Alkylation, Reliance Refinery, Jamnagar, Gujarat |
Instrumentation AMC & Field Inst. Modification |
Reliance Industries Limited |
2012-13 |
79,500 |
Essar Oil Refinery Expansion, Jamnagar, Gujarat |
Instrumentation works for ETP & Desalination Unit. Train-1 |
ESSAR Projects (India) Ltd |
2011 |
233,916 |
BUTENE-1- Reliance Industries, Hazira, Surat, Gujarat |
Installation of Instrumentation Works |
Reliance Industries Limited |
2010 |
71,500 |
CFU, PP, Coker & Alkylation-Reliance Refinery, Jamnagar, Gujarat |
Instrumentation AMC & Field Inst. Modification |
Reliance Petroleum Limited |
2010-11 |
107,500 |
KCIL-FORMALDHYDE UNIT |
Supply & Installation of Electrical & Instrumentation Works |
Kanoria Chemical India Ltd, Consultant- Uhde India Pvt. Ltd |
2010 |
80,555 |
POLY ISCOYNATE UNIT |
Supply & Installation of Electrical & Instrumentation Works |
EPC Aker Power gas Pvt. Ltd, Client: Bayer Technology Services |
2010 |
76,111 |
REPLICA Plant, Kanpur, Uttar Pradesh |
Supply & Installation of Electrical & Instrumentation Works |
Johnson Matthey Chemical India Pvt Ltd, Consultant: Aker Solutions |
2010 |
72,611 |
30 MW Power Plant |
Supply and Erection of Instrumentation Works |
Shree Virangana Steels Ltd |
2009 |
19,000 |
CFU, PP, Coker & Alkylation-RIL Refinery, Jamnagar |
Instrumentation AMC & Field Inst. Modification |
Reliance Industries Limited |
2009-10 |
101,655 |
DHDS-2 – Reliance Refinery Jamnagar |
Instrumentation Erection Works |
Reliance Industries Limited |
2009 |
43,500 |
HPU System in Coker-Reliance Refinery, Jamnagar |
Instrumentation Erection Works |
Reliance Industries Limited |
2009 |
10,000 |
LNUU 471 Compressor; FCC and Crude-2 of Reliance Refinery Jamnagar |
Instrumentation Erection Works |
Reliance Industries Limited |
2009 |
26,250 |
Sulphur Unit 672 & 431; Reliance Refinery, Jamnagar |
Instrumentation Erection Works |
Reliance Industries Limited |
2009 |
35,000 |
Wire Line Project Hyderabad |
Splicing |
Reliance Infocom Engineering Pvt Ltd |
2009 |
99,300 |
Wire Line Project Orissa |
Splicing |
Reliance Infocom Engineering Pvt Ltd |
2009 |
12,835 |
WIN Project East Godavari District |
Splicing |
Reliance Infocom Engineering Pvt Ltd |
2008 |
821,116 |
WIN Project Kamman & Meheboob Nagar & Ananthpur |
Splicing |
Reliance Infocom Engineering Pvt Ltd |
2008 |
47,000 |
Wire Line Project Hyderabad |
Splicing |
Reliance Infocom Engineering Pvt Ltd |
2007 |
64,916 |
HGU - Part A –( EPCC-06), HPCL Visakha Refinery Modernization Project at Vizag, Andhra Pradesh |
Supply & Installation of Instrumentation works |
End User: HPCL, Visakhapatnam EPC: Technip FMC |
2020 |